Barnsley Homes Standard Programme 20/21

13/07/2020 - Barnsley Homes Standard Programme 2020/21 (Cab.18.3.2020/15)

RESOLVED:-

 

(i)        that approval be given to the nine main Barnsley Homes Standard schemes, stand-alone elemental schemes and the Programme of batched replacements, releasing resources as detailed in the report now submitted;

 

(ii)       that Berneslai Homes be authorised to progress schemes within the new Property Repairs and Improvement Partnership (PRIP) 2020 contract or to appoint a suitable contractor for proposed elemental schemes and following a procurement exercise and containment of costs within the approved sums;

 

(iii)      that the added Social Value delivered by the PRIP 2020 as set out in paragraph 5.2 of the report be noted; including use of directly employed local staff and over 30 directly employed apprentices; and

 

(iv)      that the Carbon Saving efficiency measures, and anticipated reductions to tenant’s energy bills, as set out in paragraph 3.5 of the report be noted.


 