The Glassworks - Appointment and Delivery of RIBA Stage 4 Design and Associated Project Management/Cost Consultancy Service (Cab.14.6.2017/12)

Minutes:

RESOLVED:-

 

(i)        that the procurement options considered for services required for the delivery of RIBA Stage 4 design work, associated project management and cost consultancy services for the Glass Works development, as set out in the report submitted, be noted;

 

(ii)       that the appointment of Turner and Townsend be approved, via a direct call-off from the Land Solve framework for project management and cost consultancy services;

 

(iii)      that the commissioning of NPS Barnsley for the delivery of RIBA Stage 4 architectural and mechanical engineering services, with Mott Macdonald commissioned directly for civil and structural engineering and associated services via a procurement framework, be approved;

 

(iv)      that the Executive Director Core Services and Executive Director Place, in consultation with the Place Cabinet Spokesperson, be authorised to make variations to these appointments if required to progress the contract in a timely way; and

 

(v)       that the release of up to £1.7m (subject to final confirmation following the tender process) included as part of the Better Barnsley Phase 2 scheme, to be funded via prudential borrowing, be approved.