To seek approval to undertake improvement works to the Council’s high rise properties, as required.
RESOLVED that Cabinet approves:-
1. The project to carry out required remedial works through a tendered planned programme of works to be complete predominately within the 2023-24 financial year; and
2. The required HRA funding for the project up to the total estimated cost of £1.150M.
Publication date: 22/09/2022
Date of decision: 21/09/2022
Decided at meeting: 21/09/2022 - Cabinet
Effective from: 28/09/2022