To inform Cabinet of, and to seek approval for, the replacement of suspended timber ground floors and associated works to Council properties in Staincross, Mapplewell.
Decision:
RESOLVED that Cabinet:-
1.
Approves the overall Timber Floor Replacement
Programme and that the associated resources be drawn down on a
phased basis;
2.
Approves the commencement of an initial pilot
scheme, as phase one of the Timber Floor Replacement Programme,
specifically relating to two identified Council dwellings within
Staincross, Mapplewell;
3.
Approves that the release of the subsequent phases
of the programme be at the discretion of the Section 151 Officer/
Executive Director Place, subsequent to gaining satisfactory cost
estimates to support the delivery of the scheme within the
identified resources; and
4. Authorises the appointment of Berneslai Homes Construction Services to undertake the works to all phases of the programme.