Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
RESOLVED:-
1. The continued delivery of the individual elements of the Glass Works scheme was approved and the projected scheme opening date of September 2021 was noted.
2. To progress / accept external funding bids to enable the identified scheme enhancements to take place at no additional call on the Council’s resources was approved.
3.
The Executive Director Core services be authorised
to apply for any necessary consents, license arrangements, footpath
diversions, traffic regulation orders, closure orders and side road
orders that may be required to complete the scheme.
4. The Executive Director Core Services be authorised to extend the Development Management contract with Turner and Townsend to reflect the revised construction completion and scheme opening dates.
5. The Executive Directors Core Services and Place, in consultation with Cabinet Spokespersons for Core Services and Place, be authorised to enter into contract with external funding bodies awarding funding to support the delivery of the Glass Works project.
6.
The appointment of a contractor to build the Market
Gate Bridge as set out in section 5.5 to 5.9 of the report be
approved
7. Progress with the leasing of the Glass Works scheme was noted and the forward strategy as set out in section 5:10 to 5:16 of the report was approved.
Publication date: 10/02/2021
Date of decision: 10/02/2021
Decided at meeting: 10/02/2021 - Cabinet
Effective from: 17/02/2021