Capital Programme Performance Year Ending 31st March 2020 (Cab.10.6.2020/9)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Decisions:
RESOLVED:-
(i) that the final position of the 2019/20 Capital Programme which totals £140.9m, as set out in the report now submitted, be noted;
(ii) that project scheme slippage and the associated funding into future years to allow scheme completion, totalling £16.1m, be approved;
(iii) that approval be given to the project net re-phasing of budgets and associated funding into 2019/20, totalling £4.7m;
(iv) that a total net increase in scheme costs, funded from unallocated resources in 2019/20 totalling £1.7m be approved;
(v) that the new schemes approved and included within the capital programme during the quarter totalling £46.5m be noted;
(vi) that it be noted that all schemes in delivery during 2020/21 be reviewed in respect of deliverability risk, financial risk and other risks in the aftermath of the Covid-19 pandemic; and
(vii) that all schemes that are due to commence during 2020/21 be reviewed in terms of both ongoing appropriateness and in respect of deliverability risk and financial risk in the aftermath of the Covid-19 pandemic, as outlined in the Council’s Financial Recovery Strategy, be noted.
Publication date: 16/06/2020
Date of decision: 10/06/2020
Decided at meeting: 10/06/2020 - Cabinet