Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
RESOLVED:-
(i) that delivery of the Glass works scheme continues towards a projected scheme opening in 2021, as detailed in the report now submitted;
(ii) that the analysis of the impact of the Covid-19 emergency on the Glass Works development be noted;
(iii) that the measures being put in place to support the recovery of the Glass Works from the Covid-19 emergency be noted; and
(iv) that a further report be received when the longer term impacts of the Covid-19 emergency on the Glass Works scheme are fully understood.
Publication date: 10/06/2020
Date of decision: 27/05/2020
Decided at meeting: 27/05/2020 - Cabinet
Effective from: 03/06/2020
Accompanying Documents: