To approve the funding for demolition, associated services and temporary highway works to the Junction of Eldon Street and Midland Street to facilitate a left turn for traffic onto Eldon Street.
RESOLVED:-
(i) that the Service Director Regeneration and Culture be authorised to appoint Henry Boot Contractors using the existing partnering agreement to undertake the demolition works and associated temporary highway works of 35 Eldon Street, Barnsley including all surveys required for safe demolition of the site and reconfiguration of the highway; and
(ii) that the Service Director Regeneration and Culture be authorised to appoint successful tenderers for all additional survey work required for demolition; and/or consider whether the works, services or goods can be provided in-house, in compliance with the Council’s Contract Procedure Rules, subject to value for money considerations.
Publication date: 16/06/2020
Date of decision: 10/06/2020
Decided at meeting: 10/06/2020 - Cabinet
Effective from: 17/06/2020