Digital Media Centre/The Core Conversion (Cab.20.3.2019/13)

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decisions:

RESOLVED:-

 

(i)        that the Executive Director Place be authorised to undertake the necessary steps to secure delivery of the project;

 

(ii)       that the Executive Director Core Services in consultation with the Executive Director Place be authorised to:

 

·         Negotiate the terms and conditions of any Funding Agreement and that Cabinet delegate the final approval of the terms of the Grant Funding Agreement to the Cabinet Spokesperson Place;

 

·         Conclude the approval and funding process with Sheffield City Region Combined Authority (SCR CA), accept tenders, appoint where necessary a contractor to implement the delivery of the scheme, subject to the costs being contained within the scheme;

 

(iii)      that the Service Director Regeneration and Property be authorised to:

 

·         In compliance with the Council’s Contract Procedure Rules, and subject to any procurement requirements specified by the funder, seek tenders where necessary for any aspect of the project and appoint the successful tenders; and/or consider whether the works, services or goods can be provided in-house, subject to value for money considerations; and

 

(iv)      that grant funding from Sheffield City Region Investment Fund (SCRIF) totalling £2.125m towards the total cost of the scheme be accepted.

Publication date: 22/03/2019

Date of decision: 20/03/2019

Decided at meeting: 20/03/2019 - Cabinet

Effective from: 27/03/2019