Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
RESOLVED:-
(i) that the Capital Programme Performance Quarterly update for the period ending 30th September, 2016 and the overall five year Capital Programme positions, as detailed in the report now submitted, be noted;
(ii) that approval be given to the 2016/17 scheme slippage totalling -£0.274m and scheme re-phasing totalling -£23,000m, as set out in paragraphs 4.4, 4.5 and Appendix B of the report now submitted;
(iii) that the total net decrease in scheme costs in 2016/17 of -£0.803m, (paragraph 4.6 and Appendix B refer), the net increase in scheme costs in future years totalling £0.353m and the adjustments to the capital programme plans to reflects these changes be approved; and
(iv) that the two new proposed schemes totalling £0.654m, as described in paragraphs 5.1 to 5.5 of the report submitted, be approved.
Publication date: 06/12/2016
Date of decision: 30/11/2016
Decided at meeting: 30/11/2016 - Cabinet
Effective from: 07/12/2016